Sunday – ended working longer than I expected on the rental

This was day 2 since I came in and started working on the rental property. Now that I think of it, it’s actually day 3 because I had came in sometime last week to prime the walls before painting.

The goal was to finish properly securing the sliding glass door to the walls and to re-insulate and replace the rotted wood we found yesterday

I planned for 4 hours of work so that I could enjoy my Sunday with my girlfriend. That did not work out.

However, the door was installed and the job was completed in its totality.

Sunday 10-28-24 tasks finished

  • Sliding glass door in kitchen was completely installed
  • Rotted wood and insulation was replaced
  • Baseboards in the rooms and bathrooms were cleaned.
  • Room walls were dusted and cleaned to make easier to paint.
  • Toilet was cleaned again to see if more of the stains could be removed.

Sunday hours worked: 8

Total hours on house: 20